New Bedford has roadwork sites for the upcoming week of June 29, 2020 –July 03, 2020

image_pdfimage_print

The City of New Bedford has roadwork sites for the upcoming week of June 29, 2020 –July 03, 2020 and they are as follows:

Eversource:

Eversource will replace the gas mains at the following locations:

• Kings Hwy – Tarkiln Hill Rd. to Mt Pleasant St.
• Summer St. from Durfee Ct. to Locust St.
• Hill St. from Hillman St. – Mill St.
• Hillman St. from County St. – Pleasant St.
• Cottage St from Parker St – Campbell St

Eversource will be doing final street and sidewalk restoration at various locations city-wide

Other:

• Contractor (PA Landers) to continue drainage work at MassDOT Project #606709, New Bedford- Roadway Reconstruction and Related Work (including signals) along a section of Kings Highway and Tarkiln Hill Road, Construction to take place during regular working hours (Monday – Friday), police details and traffic controls will be in place.
• Department of Public Infrastructure will be filling potholes on a continuous basis throughout the city.
• Contractor (P Gioioso and Son) is scheduled to begin the replacement of the Nelson St. water main between Crapo St. and County St. During working hours Nelson St. may be closed to thru traffic with access by local traffic only. Traffic will be directed to either Jouvette St. or Scott St. Detour signage, police details and traffic controls will be in place.
• Department of Public Infrastructure conducting its annual street sweeping program city-wide.
• The contractor (WES Construction) is scheduled to continue construction of the new pumping station and installation of the site utilities at the Front St./ Elm St. site. Elm St, between JFK Memorial Highway (RTE 18) and Macarthur Dr. will be closed to westbound traffic. Westbound traffic will be detoured via MacArthur Drive. There will be detour signage and traffic controls in place.
• Due to ongoing construction at the High Hill Reservoir residents may experience discolored water. The water is safe, and the discoloration will be temporary. We recommend allowing the water to settle for a few hours and then flushing your service line by letting the bathtub run for a few minutes until the water clears.

** Please note: Contractors will continue to follow guidelines and protocol regarding COVID-19 social distancing while conducting work in construction zone.

Due to the current COVID-19 situation the Department of Public Infrastructure will be closed to the public entry. Office staff is available to assist by email and telephone.

About NewBedfordGuide

Check Also

Boston man allegedly aims laser pointer at Coast Guard helicopter trying to land at Mass General Hospital

“BOSTON – A Boston man was arrested today for allegedly aiming a high-powered laser pointer …

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Translate »