Roadwork in New Bedford week of August 15, 2016 – August 19, 2016

image_pdfimage_print

New Bedford / Fairhaven Bridge:

•Please be aware of detours and traffic delays, follow signs posted. Acushnet Ave & Wamsutta St Railroad Bridge:

•Contractor will be working on miscellaneous items throughout the project.

•The roadway closure at Acushnet Ave & Wamsutta will remain closed. Please follow detour signs.

Coggeshall St Sewer Separation:

•The Contractor will continue installing the drain along Coggeshall St between Veterans Memorial Way and Mitchell St.  There will be access to all businesses within the work zone.

Other:

•MASSDOT will be performing bridge repairs at Phillips Rd. over the RT 140 location.

•Contractor will be building the Cove Walk between West Rodney French Blvd. and Cove Rd.

•Contractor will be working on miscellaneous items on Bessey St from Acushnet Ave to the Acushnet town line.

•Contractor will be working on miscellaneous items on Tacoma St from Wildwood Rd. Westerly to the end.

•Contractor will be working on miscellaneous items on Rotch St between Hawthorn St to Maple St.

•Contractor will be working on excavating and grading Maxfield St from Liberty St. to Lindsey St.

•Hydrant flushing on dead ends in the city. This may cause a temporary loss of water pressure.

About NewBedfordGuide

Check Also

New Bedford Fire Department, Police, EMS respond to partial pier collapse

NEW BEDFORD, Mass.: On Friday afternoon, the New Bedford Fire Department raced to a reported …

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Translate »