New Bedford has roadwork sites for the upcoming week of September 18, 2023 – September 22, 2023

image_pdfimage_print

The City of New Bedford has roadwork sites for the upcoming week of September 18, 2023 – September 22, 2023, and they are as follows:

Eversource will be working on gas main relays and services on:

• Main relay on Berkley St from Commonwealth Ave to end of road
• Main relay on Church St from Carlisle St to Shaw St
• Main relay on Hudson St from Brock Ave east to end of main
• Main relay on Longwood Ave from Commonwealth Ave to end of road
• Main relay on Rockdale Ave from Allen St to Bluefield St
• Regulator work on Potter St at Rockdale Ave headed east towards Nashua St
• Services on Gaywood St from Brownell Ave to end of road
• Services on Lynwood St from Brownell Ave to end of road
• Services on Pauline St from Brownell Ave to end of road
• Services on Sheldon St from Brownell Ave to end of road

Other:
• Contractor (PA Landers) will be working at varies locations throughout the city on roadway and sidewalk patches.
• Contractor (PA Landers) will be working at MassDOT project #609201, located at the intersection of Acushnet Ave & Peckham Rd/Sassaquin Ave.
• Contractors (PA Landers and various utility companies) will be working at MassDOT’s Kings Highway project. Minor traffic impacts and lane shifts required.
• Contractor (PA Landers) will be working on a road reconstruction project at Acushnet Ave from Tarkiln Hill Road to Monmouth Street.
• Contractor (PJ Keating) will be milling the roadway surface at Acushnet Ave from Tarkiln Hill Road to Monmouth Street. Acushnet Avenue between the section of Tarkiln Hill Road to Monmouth will be shutdown to all traffic while work is taking place. Police details will be in place.
• Contractor (PA Landers) will be working on a road reconstruction project at Wood Street from the town line to Church Street.
• Contractor (PJ Keating) will be milling the roadway surface at Wood Street from the town line to Church Street. Wood Street between the section of the town line to Church Street will be shutdown to all traffic while work is taking place. Police details will be in place.
• Contractor (PA Landers) will be working on Braley Rd Sidewalks between Acushnet Avenue and Phillips Road.  Minor traffic impacts and lane shifts required.
• Contractor (SCR Constructors) will continue site work at the future South Coast Rail station platform locations in the city. (Church St at Carlisle St and Wamsutta St at Acushnet Ave.) If you have questions, please email the project team at SouthCoastRail@dot.state.ma.us
• Contractor (SCR Constructors) will continue site work at the future pedestrian bridge across Route 18 impacting parking along Purchase Street between Willis Street and Pearl Street and at the Division of Career Services on Acushnet Avenue. Temporary detours may be in place pending construction activities occurring.  If you have questions, please email the project team at SouthCoastRail@dot.state.ma.us
• Contractor (Middlesex Corp) will be working on Nash Rd between Church St and Mt. Pleasant St. Traffic will be reduced to one lane and will have police details on site to assist with traffic.
• Contractor (Newport) will be working on Nash Rd between Church St and Mt. Pleasant St. Traffic will be reduced to one lane and will have police details on site to assist with traffic.

About Michael Silvia

Served 20 years in the United States Air Force. Owner of New Bedford Guide.

Check Also

Massachusetts State Police traffic stop in Boston leads to seizure of rifle, ski mask, magazines

“On Saturday, one of our members assigned to SP Tunnels in Boston conducted a traffic …

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Translate »