The City of New Bedford has roadwork sites for the upcoming week of August 30, 2021 – September 3, 2021 and they are as follows:

Eversource will be working on the gas main relays and services at:
• Relaying gas main on Pleasant St working from Weld St to Austin St
• Replacing gas services on Lucas St and then Oaklawn St working from Brock Ave to W Rodney French Blvd
• Relaying gas main on Stowell St from Field St to Dartmouth St
• Relaying gas services on Tacoma St working from Wildwood Rd to Ashley Blvd
• Relaying gas main on Somerset St from Park St to Hersom St
• Relaying gas main on Phillips Rd starting from Birchwood Dr to Hillcrest Dr
• Working on the regulators on Holly St at Belleville Ave and/or Wood St at Belleville Ave

Other:

• MassDOT and the City will be hosting a Design Public Hearing Tuesday August 31st at 7:00pm for the upcoming intersection improvement projects located at Acushnet Ave/Peckham Rd/Sassaquin Ave. This will be a live virtual meeting. Additional information and weblink to register in advance for the meeting can be found on the calendar located on the City’s homepage.
• Contractor (PA Landers) will be paving final top course on Monday & Tuesday, weather permitting, at Metropolitan St from Brownell Ave to Commonwealth Ave, Maryland St from Caswell St to Conduit St, Conduit St from Maryland St to Jarry St, Hunter St from Maxfield St to Parker St and Parker St from Hathaway Blvd to Hunter St.
• Contractor (PA Landers) will continue road and sidewalk reconstruction on Purchase St from Penniman St to Clark St.
• Contractor (PA Landers) will begin work on Hathaway Rd from Rockdale Ave to the Town Line.
• Contactor (AGS) will be replacing sidewalk panels at various locations throughout the city.
• Contractor (PA Landers) will be repairing various roadway and sidewalks citywide.
• Contractor (K.R. Rezendes, Inc.) to continue work at MassDOT Project #606718, roadway reconstruction and related work (including traffic signal installation) along a section of Hathaway Rd, Nauset St and Mt Pleasant St.
• Contractor (PA Landers) to continue MassDOT Project #606709 for roadway reconstruction and related work along a section of Kings Highway from the railroad tracks grade crossing to the intersection of Church St and Tarkiln Hill Rd.
• Contractor (SCR Constructors) will continue site work at the future South Coast Rail station platform locations in the City. If you have questions, please email the project team at SouthCoastRail@dot.state.ma.us
• Due to ongoing construction at the High Hill Reservoir residents may experience discolored water. The water is safe, and the discoloration will be temporary. We recommend allowing the water to settle for a few hours and then flushing your service line by letting the bathtub run for a few minutes until the water runs clear.

Union St. Phase II Sewer Separation Project:

• Contractor (C. Naughton Corp.) will continue installing drain pipe along Union St between Sixth St and County St.
• The Contractor is scheduled to work Monday to Thursday from 7:00 am to 5:00 pm. During working hours Union St will be closed between Sixth St and Eighth St. Westbound traffic on Union St will be detoured via Pleasant St, Elm St and County St Eastbound traffic on Union St will be detoured via Spring St and Pleasant St.
• There is no work or traffic controls scheduled for Friday, September 3rd. If scheduled work is cancelled due to rain Monday to Thursday. The Contractor will work on Friday.
• Construction/detour signage will be posted and police details will be on-site to assist with traffic management.

** Please note: Contractors will continue to follow guidelines and protocol regarding COVID-19 social distancing while conducting work in construction zone.

About Michael Silvia

Served 20 years in the United States Air Force. Owner of New Bedford Guide.

Check Also

Southcoast Health recognizes “Donate Life Month” with annual New Bedford flag-raising ceremony

“NEW BEDFORD, Mass. – Community members, providers, nurses and staff gathered at St. Luke’s Hospital …

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Translate »