New Bedford roadwork sites for the upcoming week of November 21, 2022 – November 25, 2022

image_pdfimage_print

“The City of New Bedford has roadwork sites for the upcoming week of November 21, 2022 – November 25, 2022, and they are as follows:

Offices will be closed & no construction works Thursday, November 24th and Friday, November 25th.

Eversource:

Eversource will be working on gas main relays and test pits on:
• Phillips Rd from Holly Tree Lane to Route 140

Other:

• Contractor (KR Rezendes, Inc.) will be painting all pavement markings on Monday at MassDOT’s Hathaway Triangle project located at the newly signalized intersection of Hathaway Rd x Nauset St. Lane shifts required, police officers and signage will be posted during operations.
• Contractor (PA Landers) will be raising structures on Clifford St from Ashley Blvd to Acushnet Ave. Contractor will be stabilizing the site to wrap up for the winter season. Sidewalk reconstruction and top paving course to take place in the Spring 2023.
• Contractor (PA Landers) will continue curb installation and sidewalk reconstruction along a portion of Phillips Rd north of Birchwood Dr.
• Contractor (PA Landers) will be working on West Street in the vicinity of St. Luke’s Hospital raising structures in the roadway and stabilizing the site for the winter season. Final top course paving to be done in the Spring 2023.
• Contractor (PA Landers) will be working on wheelchair ramp upgrades along a portion of East Rodney French Blvd from Abbott St to Butler St.
• Contractor (PA Landers & various utility companies) will be working at the MassDOT project, Kings Highway.
• Contractor (PA Landers) will be working on various streets, citywide, completing minor repairs and installations.
• Contractor (PA Landers) will be working on sidewalk reconstruction on Union St from Sixth St to County St. Final top course paving tentatively scheduled for Tuesday, Nov. 22nd.
• Contractor (PA Landers) will be paving top course on Hazelwood Park tennis courts.
• Contractor (SCR Constructors) will continue site work at the future South Coast Rail station platform locations in the city. (Church St at Carlisle St and Wamsutta St at Acushnet Ave.) If you have questions, please email the project team at SouthCoastRail@dot.state.ma.us”

About Michael Silvia

Served 20 years in the United States Air Force. Owner of New Bedford Guide.

Check Also

Massachusetts State Police seize 4.5 kilos of cocaine, arrest 52-year old, in early morning raid

“A joint investigation earlier today resulted in the seizure of more than four kilograms of …

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Translate »