New Bedford roadwork sites for the upcoming week of August 8, 2022 – August 12, 2022

image_pdfimage_print

The City of New Bedford has roadwork sites for the upcoming week of August 8, 2022 – August 12, 2022, and they are as follows

Eversource will be working on the street milling from gas main relays on:

• Main Relay on Phillips Rd. from Holly Tree Lane to Route 140
• Main Relay on Rockdale Ave & Allen St

Eversource will be working on the street milling from gas main relays on:

• Purchase St from County St to Cove St
• Fillmore St from Myrtle St to Summer St
• Buchanan St from Myrtle St to Mt Pleasant St
• Garfield St from Myrtle St to Mt Pleasant St
• Sawyer St from Mt Pleasant St to Purchase St
• County St from Sawyer St to Purchase St
• Summer St from Fillmore St to Sawyer St
• Phillips Ave from Riverside Ave to Oneko Ln
• Brook St from Earle St to Collette St
• Shaw St from Acushnet Ave to Conduit St
• Conduit St / Hatch St from Shaw St to Covell St
• Carroll St / Priscilla St from Gould St to Rockdale Ave
• Brownell St from Brownell St #266 to Arnold St
• Armour St from Armour #122 to Arnold St
• Davis St from End of road #389 to Riverside Rd

Other:
• Contractor (PA Landers) will begin sidewalk excavation along a portion of Phillips Rd from Holly Tree Ln to Birchwood Dr.
• Contractor (PA Landers) will be working on various curb and structure adjustments on Mt. Pleasant St from New Plainville Rd to Nash Rd.
• Contractor (Eversource Electric) will be working at the MassDOT project, Kings Highway, new traffic signal operations and sign installations.
• Contractor (PA Landers) will be working on various streets, citywide, completing minor repairs and installations.
• Contractor (PA Landers) will be working on sidewalk reconstruction on Cedar St from Maxfield St to Mill St.
• Contractor (PA Landers) will be working on sidewalk reconstruction on Union St from Sixth St to County St
• Contractor (SCR Constructors) will continue site work at the future South Coast Rail station platform locations in the city. (Church St at Carlisle St and Wamsutta St at Acushnet Ave.) If you have questions, please email the project team at SouthCoastRail@dot.state.ma.us
• Contractor (C. Naughton Corp) will continue replacing water service connections. Thew crew will work north to south starting at Taber St. There will be detours during working hours via Brigham and adjacent streets as the work progresses. Signage will be posted and police details on-site with traffic management.
• Contractor (C. Naughton Corp) will complete work replacing the water main and installing fire hydrants along Clifford St between Ashley Blvd and Acushnet Ave. Work will resume west of Arlington St and proceed westerly toward Ashley Blvd. Clifford St will be restricted to local access only during working hours. There will be construction signage and police details to assist with traffic management.

About Michael Silvia

Served 20 years in the United States Air Force. Owner of New Bedford Guide.

Check Also

New Bedford’s Mayor Mitchell reacts to offshore wind energy proposals and bids

NEW BEDFORD – In a Wednesday letter to Massachusetts state officials, New Bedford Mayor Jon …

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Translate »