The City of New Bedford – Department of Public Infrastructure
Acushnet Ave & Wamsutta St Railroad Bridge:
-Contractor will be working on miscellaneous items throughout the project.
-The roadway closure at Acushnet Ave & Wamsutta will remain closed. Please follow detour signs.
Other:
-MASSDOT will be performing bridge repairs at Phillips Rd. over the RT 140 location.
-MASSDOT will be performing bridge repairs at County St and Purchase St over the I-195 East Bound.
-The Contractor is scheduled to complete final trench paving at various intersections along Ashley Blvd between Park Ave and Deane St.
-Contractor will be building the Cove Walk between West Rodney French Blvd. and Cove Rd.
-Contractor will be building an extension to the Multi use path on West Rodney French Blvd, between Hazelwood Park and Hurricane Barrier gate.
-Contractor will be installing cement concrete wheelchair ramps and sidewalks on Tallman Street, Bullard Street and Nye Street between Acushnet Avenue and Belleville Avenue.
-Contactor will be paving miscellaneous patches though out the city.
-Hydrant flushing on dead ends in the city. This may cause a temporary loss of water pressure.